Mumbai Metro | MMRDA invites bids for supply of Automatic Fare Collection systems for Line 2A, 2B and Line 7

Mumbai: The Mumbai Metropolitan Region Development Authority (MMRDA) invites global tenders for Design, Manufacture, Supply, Installation, Testing and Commissioning and Maintenance of Automatic Fare Collection (AFC) Systems for 52 Elevated Stations and AFC OCC, AFC Software Testing and Development Center (SDC) of Mumbai Metro Line 2A (Dahisar East - Dn Nagar), Line 2B (ESIC Nagar - Mandale) and Line 7 (Andheri East - Dahisar East) of Mumbai Metro Rail Project of MMRDA.
Contract No. and Title: MMRDA/MMRP/CA-33: Design, Manufacture, Supply, Installation, Testing and Commissioning and Maintenance of Automatic Fare Collection (AFC) Systems for 52 Elevated Stations and AFC OCC, AFC Software Testing and Development Center (SDC) of Metro Line 2A (Dahisar East - Dn Nagar), Line 2B (ESIC Nagar - Mandale) and Line 7 (Andheri East - Dahisar East) of MMRDA.

Key Points of Tender Notice No. MMRDA/MMRP/CA-33:
  • Completion period of the Work: Forty Two (42) months

  • Tender documents on sale: From 15.06.2018 to 30.07.2018 (up to 1200 hrs) on e-tendering portal of MMRDA. https://etendermmrda.maharashtra.gov.in

  • Cost of Tender documents: INR 11,200/-

  • Pre-bid Meeting: 02.07.2018 at 15:00 hrs.

  • Date & time of Submission of Tender online: 30.07.2018 up to 15:00 hrs

  • Date & time of Tender Closing: From 30.07.2018 (1501 Hrs) to 30.07.2018 (up to 1800 hrs)

  • Date & time of opening of Tender online: 31.07.2018 at 12:01 hrs.

  • Authority for purchase of tender documents, seeking clarifications and submission of completed tender documents: Director (System)-Metro PIU, 1st Floor, A-wing, Old Administrative Building, Mumbai Metropolitan Region Development Authority (MMRDA),
    Bandra Kurla Complex, Bandra (E), Mumbai – 400051
    Phone: 91(22) 26597552, Fax: 91(22)26594182
    E-mail: metropiu.systems@mailmmrda.maharashtra.gov.in
    https://mmrda.maharashtra.gov.in

About Mumbai Metro Line-2A, Line-2B and Line-7 Corridors:

  • Line 2A will cover approx. 18.5 km long distance from Dahisar to DN Nagar and consist with 17 elevated metro stations. It shall provide inter-connectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).

  • Line 2A will cover approx. 23.6 km long distance from DN Nagar to Mandale and consist with 22 elevated metro stations. It shall provide interconnectivity among the existing Western Express Highway, Eastern Express Highway, Western Railway, Central Railway, Mono Rail, Metro Line 1 (Ghatkopar to Versova) and Metro Line 2A (Dahisar to D N Nagar), Metro Line 4 (Wadala to Kasarvadavali) & Metro Line 3 (Colaba to SEEPZ) under implementation. A dedicated Depot is planned on this line at Mandale

  • Line 7 will cover approx. 16.5 km long distance from DN Nagar to Mandale and consist with 22 elevated metro stations. This corridor will provide inter-connectivity among the existing Western Express Highway, Western Railway, Mumbai Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to DN Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli). This corridor will also provide connectivity between Central Mumbai and Northern suburban Mumbai. It will also provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks. A dedicated Depot is planned on this Line at Dahisar.


Source: MMRDA website

Comments

Popular posts from this blog

Chennai Metro | CMRL releases map of Phase 2 metro project

NCRTC invites bids for engagement of detailed design consultant for elevated RRTS stations

Delhi Metro | CMRS to start inspection of Durgabai Deshmukh-Lajpat Nagar section